Fortum Power and Heat Oy: Järvenpää CHP Project - Process Electrical Installations and Process Instrument Installations.

Hange

Läbirääkimistega menetlus
07.02.2012 5:23 (GMT+02:00)
17.02.2012 16:00

Hankija

Fortum Power and Heat Oy Fortum Power and Heat Oy
PL 100
00048 Fortum
Finland

Hange on lõppenud

Hanke lühikirjeldus

Fortum Power and Heat Oy is planning to improve the existing district heat production capacity by installing a new combined heat and power plant (the CHP Plant) to cover the base district heat load of the city of Järvenpää, Finland.

The power plant concept consists of 76 MW fuel-power BFB boiler plant and 23 MW electric power steam turbine generator plant. The new plant is planned to be in commercial operation in the middle of year 2013.

This supply consists of process electrical installations and process instrument installations. With one announcement the candidates can express their interest for one or both of the installations. Fortum reserves the right to buy both installations from one company or divide installations to two separate companies.

Mercell Estonia OÜ

Mercelli gruppi kuuluv Euroopa juhtiv e-hanke keskkond vahendab infot ostjate ja tarnijate vahel.

Kontakt

Mercell Eesti kasutajatugi

+372 683 6785
Mercell Estonia OÜ | Põhja puiestee 21C, 10143 Tallinn, Eesti